2/01/07: Lot 86
has a new slab. |
2/02/07: Lot 69's
slab has just been poured. |
2/02/07: Lot 66
gets roof trusses. 68 already has their plywood roof in place. |
2/02/07: Irrigation
lines and trees are being put into place. |
2/02/07: Work
continues on the future Desert Peak Parkway.
More curbing is
poured. |
2/02/07: Tar
paper is added to home #66. |
2/06/07: Lot 37 is
ready to be poured, Lot 38 is newly poured, and framed 35 and walled 36 are in the background. |
2/06/07: The
curbs of the future Desert Peak Parkway are poured a few feet at a time... |
2/07/07: Lot 62 has
new windows, Lot 65 gets roof tiles lifted into place. |
2/08/07: Lot 86 has
standing walls but no roof. Behind it, Lot 73 has tar paper, and Lot 74 has tiles, finished walls, and foam insulation! |
2/08/07: Landscape
piping is in place. A few multiple head lines sprout into something! Guess we'll find out in a few months! |
2/15/07: Lot 86
gets a roof... and the framing for elevation 'B' begins to take shape. |
2/14/07:
(Valentine's Day!)
Lot 62 has a full
workcrew working both inside and out. Hope they get time off to buy cards and flowers! :) |
2/22/07: Lot 72
turns from a slab into a house.
Note the little
sidewalk barely visible on the left.
(Where does that
sidewalk go? See below!) |
2/22/07: 48 hours
ago, this was a slab. Now there's a house on Lot 69! |
2/22/07: Lot 65
is going to have stone! |
2/22/07: The view
from lot 61, looking down the view fence at lots 65 to 68... |
2/22/07: One of
the parkway lamps is resting, while workmen are raising Lot 101! |
2/22/07: A
view of lots 50 to 60... and our hill! |
2/22/07:
Remember that little walkway mentioned above, near Lot 72?
Well...
|
... it connects our
little community to 25th Street! |
2/23/07: Lot 61.
With the clouds, I think this a VERY artsy picture! :) |
2/23/07: Lot 54...
your framing has started! |
2/23/07: View
from the side of Lot 62, looking north up 24th Terrace. |
2/23/07: Drywall is
delivered to Lot #1. I'm going to guess this homeowner will be closing first! |
2/23/07: Lot 69,
workmen at the truck, inside the home, and on the roof. Good job! |
2/27/07: Lot 63
has lumbar stacked in the backyard... ready for the next morning's work crew! |
2/27/07: Interesting.
Instead of speed bumps, DR Horton uses these 'tree wells' that jut out into the street.
Clever, no?
|
2/27/07: Lot 86 has
its' roof delivered. Good thing too, with those clouds looming! |
3/01/07: Lot 61
gets ductwork installed. |
3/12/07: Trees are
installed outside the fence behind lots 62-67. I guess it brings the work area back to desert landscaping. |
3/13/07: Lot 69
gets windows. Next door, lot 68 already is styrofoamed! |
3/13/07: Lot 86
gets windows. |
3/13/07: First
layer of pavement is down. Desert Peak Parkway, looking west... |
... and looking
east. You can just make out the traffic light at Cave Creek Road.
One day, we'll all
be waiting there on our way to work! |
3/13/07: Lot 1,
drywall installed. |
3/16/07: Lot 61
has windows installed, and roof tiles have been delivered. |
3/16/07: Lots
1 and 3 now have stucco! |
3/18/07: Lot 62's
garage is insulated. It's a four car garage, so I guess this will keep the 'toys' warm... or 'cool'! |